Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
product
Filter by Categories
Bricklaying
Carpentry
Construction
Design
Electrical
Gas
Green Energy
Health and safety
High voltage
Newsroom
Painting and decorating
Plastering
Plumbing
Product
Tiling
Tools and equipment

Try our free simulation training now. Get started >

R1 R2 Test Explained: What the Reading Tells an Electrician

Electrician in hard hat and mask testing circuits at a distribution board

Quick answer: The R1+R2 test measures the combined resistance of a circuit’s line conductor (R1) and protective conductor (R2) with the circuit dead. It proves the CPC is continuous and gives the figure added to Ze to calculate earth fault loop impedance: Zs = Ze + (R1 + R2). There is no fixed pass value, so compare it with the expected reading.

The R1 R2 test is one of the most informative measurements taken during the dead testing sequence of an electrical installation. It confirms the continuity of protective conductors and gives the electrician the data needed to verify circuit integrity, calculate earth fault loop impedance, and satisfy the requirements of BS 7671:2018+A4:2026. For working electricians and apprentices building towards competence, understanding what the reading actually tells you matters far more than simply recording a number on a schedule of test results.

This guide breaks down the purpose of the test, the method, the expected values, and how to interpret results correctly and safely.

What R1 and R2 Actually Measure

This is a continuity test carried out on a final circuit while it is dead. The two values represent specific conductors:

Measured together, R1 + R2 gives the total resistance of the line conductor and the CPC from the origin of the circuit to the furthest point. This combined figure confirms that the protective conductor is continuous and correctly connected throughout the circuit.

Regulation 643.2.1 requires verification of protective-conductor continuity during initial verification. For periodic inspection, the inspector determines and records the appropriate extent of inspection and testing, including any agreed limitations.

R1 R2 Test Versus the R2-Only Test

Apprentices often confuse two related checks, so it is worth separating them clearly:

Both prove the CPC is sound. The difference is whether you also capture the line conductor for the loop impedance sum. The same wander-lead technique is used to check main and supplementary bonding conductors, covered in our earth bonding guide.

Why the Test Matters

The primary purpose is to confirm the continuity of protective conductors, which underpins automatic disconnection of supply under fault conditions. If the CPC is broken, high in resistance, or incorrectly terminated, the protective device may not operate within the required disconnection time, leaving exposed conductive parts dangerous during a fault.

The reading also feeds directly into loop impedance verification. The measured R1 + R2 value is used to establish the earth fault loop impedance (Zs) for the circuit:

Zs = Ze + (R1 + R2)

Here, Ze is the external earth fault loop impedance measured at the origin. By adding the measured R1 + R2 to Ze, the electrician can calculate the expected Zs without carrying out a live loop test at every point. That is useful where live testing is impractical or where RCD nuisance tripping would interfere. To check a measured Zs against the 0.8 rule of thumb, use our measured earth fault loop impedance check.

The calculated Zs is then compared against the maximum permitted values in BS 7671 Tables 41.2 to 41.5 for the relevant protective device type and rating, after allowing for conductor temperature (see below). If the calculated figure exceeds the maximum, disconnection times cannot be guaranteed and the circuit does not comply.

Correct Isolation Comes First

DIN-rail power supply, terminals and wiring inside an electrical control panel

No continuity testing takes place on a live circuit. Before any measurement:

Failing to account for lead resistance can push a marginal circuit into apparent non-compliance, or mask a genuine fault. Getting isolation and nulling right is what makes the rest of the test trustworthy.

If you want to rehearse the isolation sequence before you test, work through it step by step in our Safe Isolation Simulator.

How the Test Is Carried Out

There are two recognised methods for a standard radial circuit, and the choice depends on the circuit and site conditions.

Method 1: Temporary Link at the Board

A temporary link connects the line conductor to the CPC at the distribution board. The electrician then measures the resistance between the line and CPC terminals at each point on the circuit, such as socket outlets, lighting points and switches. The highest reading, normally at the furthest point, is the R1 + R2 value for the circuit.

This method confirms CPC continuity and correct polarity at every accessory tested, and it gives you the R1 + R2 figure for the Zs calculation, which makes it the usual choice for radial circuits on a new installation.

Method 2: The Wander Lead Method

One lead of the low-resistance ohmmeter is connected to the main earthing terminal, and a long wander lead is taken to each point on the circuit to measure between the main earthing terminal and the CPC. This gives R2 only, not R1 + R2, so it proves the CPC (or a bonding conductor) is continuous but does not on its own give the figure for the Zs calculation. Null the wander lead before you start, because its length adds noticeable resistance. Ring final circuits use their own cross-connect method, covered below.

Whichever method you use, remove the temporary link and reinstate the circuit correctly before energising. Leaving a link in place is a serious error.

Once continuity is confirmed on every circuit, the next dead test in the sequence is the insulation resistance test.

Ring Final Circuits Are Different

A ring final circuit is not tested the same way as a radial, and this trips up a lot of people. Regulation 643.2.1 requires an extra step because you have to prove the ring is actually a ring:

Diagram of a ring final circuit showing the three end-to-end continuity readings: r1 line to line, rn neutral to neutral and r2 cpc to cpc.
On a ring final, each conductor is measured end to end: r1, rn and r2.

With the ring correctly cross-connected, line-to-CPC readings can rise towards the midpoint when line and CPC resistances per metre differ. The midpoint maximum approaches (r1 + r2)/4; the variation depends on conductor sizes and ring length. Record the highest appropriate R1+R2 reading. Sockets on spurs add the resistance of the spur conductors. Investigate anomalies using the circuit layout, end-to-end results and possible parallel paths rather than diagnosing an incorrect cross-connection from a midpoint rise alone.

Understanding the Reading

A number on its own means little without something to compare it against. There is no single pass or fail figure.

For any circuit, the expected R1 + R2 can be calculated from the conductor cross-sectional areas, the cable length, and the resistance per metre of the conductors. Published reference values for copper conductors let you predict a target figure, and a measured value close to that target indicates sound, continuous conductors.

Consider what different readings suggest:

Temperature affects conductor resistance too. The maximum Zs values in BS 7671 Tables 41.2 to 41.4 assume the conductors are at their maximum operating temperature, commonly 70°C, but you test them cold. So compare like with like: either check Ze + (R1 + R2) against 80% of the tabulated maximum, the rule of thumb given in Appendix 3 of BS 7671, or compare it with the maximum values already adjusted for test temperature in IET Guidance Note 3 or the On-Site Guide. If you use GN3 or On-Site Guide values, say which publication in the remarks column of the schedule. The IET explains the approach in Wiring Matters.

Common Errors and How to Avoid Them

A few recurring mistakes undermine the reliability of the result:

A disciplined routine of isolate, prove dead, null the instrument, test methodically, and cross-check against calculated values will catch most of these. 

Understanding the R1 R2 test takes practice as well as technical knowledge. Tradefox offers practical electrical simulations that let you revisit key skills and build confidence at your own pace.    

Switch room corridor lined with electrical panels

Recording and Compliance

The R1 + R2 values, along with the derived Zs, are recorded on the schedule of test results that accompanies an Electrical Installation Certificate, Minor Electrical Installation Works Certificate, or Electrical Installation Condition Report. Accurate recording is a professional requirement, and the figures form part of the evidence that the installation meets the standard. Note that the model forms were updated under Amendment 4, so always work to the current schedule.

For anyone working towards inspection and testing qualifications, competence here is a core assessed skill. It is a genuine safety verification, not a box-ticking exercise.  

Practise this in a simulation

Practise R1+R2 continuity testing on virtual circuits before you do it for real.

Try the Electrician course

FAQs

What is a good R1+R2 reading?

There is no single pass figure. Work out the expected value from the cable length and the resistance per metre of the conductors, then check the measured reading is close to it. For example, 2.5mm² twin and earth with a 1.5mm² CPC is about 19.51mΩ per metre at 20°C, so a 20m run should read around 0.39Ω.

What is the difference between R1+R2 and R2?

R1+R2 is the combined resistance of the line conductor and the CPC, measured with them linked at the board, and it feeds the Zs calculation. R2 is the CPC alone, usually measured with a wander lead from the main earthing terminal.

Why do you null the test leads?

Test leads have their own resistance, often 0.1Ω to 0.3Ω or more. Nulling, or zeroing, the instrument removes that from every reading so the result reflects only the circuit conductors.

How do you test R1+R2 on a ring final circuit?

Measure end-to-end r1, rn and r2, complete the line-neutral cross-connection check, then remove those links. For the R1+R2 stage, cross-connect the line of one leg to the CPC of the opposite leg and join the remaining line and CPC. Measure at every socket, including spurs. Unequal line and CPC resistances can produce a midpoint rise towards (r1+r2)/4; interpret the pattern against the circuit and record the highest appropriate R1+R2 result. Remove the links and reinstate the circuit before energising.

Is R1+R2 a live or dead test?

It is a dead test. The circuit must be isolated, locked off and proved dead with a GS38 voltage indicator and proving unit before any measurement is taken.

Do R1+R2 readings need temperature correction?

Yes, when you use them to check against maximum Zs values. Readings are taken cold, but the maximum Zs values in BS 7671 assume conductors at operating temperature. The usual approach is to compare Ze + (R1 + R2) with 80% of the tabulated maximum (the rule of thumb in Appendix 3 of BS 7671), or with the temperature-adjusted maximum values in IET Guidance Note 3 or the On-Site Guide.

Key Takeaways

The R1 R2 test verifies the continuity of the line conductor and protective conductor across a final circuit, confirms the CPC is sound, and provides the R1 + R2 value used to calculate earth fault loop impedance. Carried out dead, proved dead to GS38, nulled correctly, and interpreted against a calculated expected value and the BS 7671 maximum Zs tables, it gives clear evidence of circuit integrity and compliance. Read properly, the number is not just a figure on a certificate. It is confirmation that the safety of the installation can be relied upon. 

Share article

Was this article helpful?

Latest news and articles, direct from Tradefox.

R1 R2 Test Explained: What the Reading Tells an Electrician