Development: Main construction announced 18 November 2026
Main construction has begun on a new 400kV electricity substation in Somerset that will connect one of Europe’s largest planned battery factories to the national grid.
National Grid Electricity Transmission is building the substation near Woolavington, with Balfour Beatty’s power transmission and distribution business as its delivery partner. It will connect the Gravity Smart Campus, home to the Agratas battery manufacturing plant.
Key facts
- Work now under way includes steel structures and above-ground electrical equipment.
- Three supergrid transformers are due to arrive in early 2027.
- Until the substation is finished, the site is being powered through two interim 33kV connections built by National Grid Electricity Distribution.
- Normal site hours are 8am to 6pm on weekdays and 8am to 1pm on Saturdays.
- A £530,000 community fund will open for applications in 2027.
Agratas expects the plant to create about 4,600 jobs. National Grid said the project is part of its five-year, £40bn investment in the electricity network.
Why it matters
Transmission substations are among the biggest sources of high voltage work in the UK. Each one needs electrical fitters, jointers, commissioning engineers and civils teams, often for several years.
With dozens of similar projects planned under the Great Grid Upgrade, demand for HV-qualified electricians and authorised persons is expected to stay strong.
Sources · National Grid
Main image: electrical substation with transformers and power lines. Photo by Jose Manuel Esp on Unsplash.
Share article
Was this article helpful?
Thanks — that helps us improve these guides.