Development: Programme update reported 26 November 2026
Work on a new platform and a second entrance at Oxford railway station is due to start early next year, Network Rail has said.
The next phase of the station’s upgrade includes:
- a fifth platform
- new road and rail bridges at Sheepwash, north of the station
- a new western entrance
The design-and-build job was priced at £40m when it was announced last year.
Network Rail dropped plans to put it out to open tender in January. It will use its existing contractor frameworks instead. It hopes to award the contract before the end of December, as long as government funding is released.
The timetable
Preparation work is due early in 2027, followed by work on the bridges and the platform.
The western entrance will be built through 2028 and 2029. The new facilities are due to open by summer 2029.
Architects Hawkins\Brown have started redesigning the entrance. The new designs are expected to go through planning by the middle of 2027.
Roger Dudman Way is expected to close to through traffic for about 20 months. Network Rail says it is looking at working around the clock to shorten that.
Tom Pierpoint, Network Rail’s industry programme director for the Great Western route, said the platform and entrance were a really important part of getting the station ready for the future.
Why the station needs it
Oxford is one of the busiest stations in the South East, and more trains are planned.
Network Rail has revised its passenger forecasts. It has taken account of East West Rail, the possible reopening of the Cowley Branch Line and a planned Universal theme park in Bedfordshire.
A troubled upgrade
The project follows the replacement of the Botley Road railway bridge next to the station. The road reopened in September after being shut for nearly three and a half years.
The cost of the wider station upgrade has risen from £161m to £237m. That figure does not include the full cost of this final phase.
Separate, longer-term plans for a new eastern entrance and development around Becket Street will go out to public consultation next summer.
What it means for trades
The job will bring rail civils, bridge building, platform construction and station fit-out work to Oxford over the next three years.
The main contractor has not been named. Subcontract packages for groundworks, concrete, steel, mechanical and electrical work and finishes are likely to follow once it is.
Anyone who wants to work on the railway will need the right site safety cards, such as a Personal Track Safety (PTS) card for work near the line.
Sources · Construction Enquirer · Network Rail: Oxfordshire Connect · Network Rail: Sheepwash bridge upgrades · Find a Tender pipeline notice
The eastern side of Oxford station, January 2025. Photograph by DS Pugh · CC BY-SA 2.0.