Chase retentions before Christmas shutdown, plastering contractors told

Plasterer applying plaster to a wall with trowels

Plastering, drylining and interiors contractors are being urged to chase overdue payments and retentions now, before clients and main contractors close for Christmas.

The Finishes and Interiors Sector (FIS) says firms have about five weeks before the break. Last year, it says, one construction business shut from 23 December until early January and did not respond to emails, calls or texts, leaving subcontractors unable to chase what they were owed.

What FIS advises

  • Chase retentions. Many firms have large sums outstanding. Log when retention is due, at practical completion and at the end of the defects period.
  • Back up every application. Give full detail and supporting evidence so there is little room to challenge it, and meet the client’s quantity surveyor to go through it.
  • Stick to the dates. A late application can slip into the next payment cycle, pushing cash into the new year.
  • Ask about shutdowns. Find out when the other side’s office closes and get assurances that payment issues will be settled first.
  • Escalate early. If progress stalls, go to senior managers and, if needed, the client.

If they will not pay

When retention is due, contractors can apply for it. If no payment notice or pay less notice is issued, the amount applied for becomes due.

If the other side still refuses to engage, FIS says firms can start adjudication. Low value schemes and summary procedures offer fixed adjudicator fees, which can make it affordable for smaller sums.

FIS stresses this is not a call for confrontation, but for getting information in early so payment arrives on the final date. It also encourages members to sign the Conflict Avoidance Pledge.

Why it matters

Specialist contractors in housebuilding typically give 60 to 78 days of credit, FIS research found earlier this year. A missed payment before Christmas can leave a small plastering firm paying wages and suppliers for weeks with no money coming in.

Sources · FIS · FIS: housebuilding supply chain research

Main image: plasterer at work. Photo by Sasun Bughdaryan on Unsplash.

More plastering news

Share article

Was this article helpful?

Real, sourced news for the UK trades.

Chase retentions before Christmas shutdown, plastering contractors told

Lien secret