Development: Main works contract reported 26 November 2026
A £210m contract has been signed to turn a half-finished motorway junction near Cheltenham into a full interchange, with main works starting early next year.
Galliford Try will rebuild junction 10 of the M5 for Gloucestershire County Council. The whole scheme is worth £372m.
At the moment, drivers can only leave the M5 at junction 10 when heading south, and can only join it heading north. Traffic going the other ways has to cross Cheltenham or use junction 11.
What will be built
The works have three parts, which will be built at the same time:
- The existing A4019 bridge over the motorway will be knocked down. Two new bridges will carry a roundabout over the M5, with four new slip roads.
- A new 1.4km West Cheltenham Link Road will be built.
- Part of the A4019 Tewkesbury Road will be made into a dual carriageway, between Withybridge Lane and Gallagher Retail Park.
The plans also include an underpass for walkers, cyclists and horse riders, and an eastbound bus lane on the A4019.
When it will happen
Main works are due to start in early 2027. The existing slip roads will close for about two years.
Physical work should finish in spring 2029. Snagging and handover will run until spring 2031.
Preparation is already done. That includes archaeological digs, moving utilities, work to protect wildlife and setting up site compounds.
Why it matters
The council says the scheme will help unlock more than 20,000 new homes, including 7,000 affordable homes.
It will also serve the £1bn Golden Valley development and the National Cyber Innovation Centre next to GCHQ.
Galliford Try’s chief executive, Bill Hocking, said infrastructure remained a key part of the company’s growth plans.
A long road
The council first brought Galliford Try in under an early contractor deal in June 2023.
The Transport Secretary gave planning consent in June 2025. In January this year, the government put in another £71.5m. The council’s cabinet approved the main works in June. At that point it expected work to start this autumn.
What it means for trades
This is one of the biggest highways jobs in the South West. Over the next four years it is likely to need groundworkers, concrete gangs, steel fixers, drainage teams, plant operators and traffic management crews.
The 20,000 homes it is meant to unlock would bring years of work for housebuilding trades in the area.
The deal was announced in the same week the government scrapped two road schemes in the East Midlands to fund defence.
Sources · Construction Enquirer · Gloucestershire County Council: £71.5m funding · Scheme information · SoGlos
The M5 approaching junction 10 near Cheltenham. Photograph by Philip Halling · CC BY-SA 2.0.