Announcement: 9 November 2026
National Grid has appointed BAM UK & Ireland to deliver southern converter station works for a proposed electricity link between Scotland and England.
Eastern Green Link 3 would connect Peterhead in Aberdeenshire with Walpole in Norfolk, carrying electricity through a combination of subsea and underground cables.
National Grid said the connection could transmit enough electricity to supply about two million homes and help reduce constraints on the network.
The proposed route includes approximately 436km of subsea cable in English waters, coming ashore on the Lincolnshire coast north of Anderby Creek.
The appointment prepares the project for delivery, but construction remains subject to consent.
The scheme is being developed jointly by National Grid Electricity Transmission and SSEN Transmission as part of wider investment in Britain’s electricity network.
Source: nationalgrid.com.
Archive report: 9 November 2026. Added to Tradefox on 25 November 2026.
Illustrative electricity transmission infrastructure; not Eastern Green Link 3. Photo: Adem Percem / Unsplash. Image source; Unsplash License.
Share article