National Grid construction update, November 2026.
National Grid says it has installed electrical equipment for one of the main connections at its new 400 kV Wallend substation in Kent. Its November update also confirms that a distribution transformer has been put in position and that the foundations for further equipment are complete.
Work continues with contractor Balfour Beatty on the remaining connections. The next major stage is high-voltage testing, which National Grid says will begin in the coming months. Engineers will check that the equipment, cables and safety systems work together before the new substation starts operating on the transmission network.
The completed connection uses a gas-insulated busbar. Busbars carry power between pieces of equipment within a substation. Here, sections of the busbar run across the compound on steel supports between installation areas. The foundations are a separate milestone in preparing the site for equipment that is still to be installed.
National Grid is building the substation in an established industrial area on the Isle of Grain. It is intended to strengthen the transmission network and help connect NeuConnect, a new electricity link between Great Britain and Germany. The link’s developer says it is designed to carry up to 1.4 GW in either direction, giving both countries another route to import or export power.
On the UK side, the interconnector has a separate converter station. It will convert the direct current used for long-distance transmission along the link into alternating current for the British network, and reverse that process for exports. NeuConnect estimates that the link will involve about 725 km of cables on land and under the sea.
National Grid’s update sets out the next construction and testing stage at Wallend. It describes testing as expected in the coming months and gives no date for the substation to enter service. Commissioning the substation and bringing the cross-border link into use are separate milestones.
Sources · National Grid’s November construction update · National Grid’s Wallend project page · NeuConnect’s project overview
File photograph of nearby Grain power station on the Isle of Grain. The Wallend works are at a separate site. Photograph by Roger A Smith · CC BY-SA 2.0. Resized without cropping.