Free toolbox talk 17 · Groundworks

Excavations toolbox talk

Support it, inspect it, protect the edges. A free, ready-to-run briefing for UK sites.

  • 10 minutes
  • For: Groundworkers, plant operators and anyone working in or near excavations
  • Last reviewed 25 November 2026
Download free PDFPDF, 1051 KB: 8 pages, including linked source references

Why this matters

A trench can collapse without warning, even in ground that looks firm. A cubic metre of soil can weigh more than 1.5 tonnes, which is enough to crush or bury someone.

Key points

  1. Never go into an unsupported excavation where the sides could collapse. Shore it or batter it back.
  2. A competent person must inspect supported or battered excavations at the start of every shift.
  3. They must also inspect after anything that could affect stability, such as heavy rain or a fall of material.
  4. Record inspections under CDM regulation 24; event reports must not wait a week.
  5. Put barriers round the edges to stop people, vehicles and materials falling in.
  6. Keep spoil, materials and plant back from the edge so they don't overload the sides.
  7. Use a proper ladder or step access to get in and out.
  8. Check for underground services before digging, and watch for nearby walls and foundations being undermined.

Do and don’t

Do

  • Check the excavation has been inspected before you go in.
  • Use stop blocks so vehicles tipping into the trench don't go over the edge.
  • Keep a ladder in place for a quick way out.
  • Report cracks, bulges or water seeping in straight away.
  • Get out if the ground starts to move.

Don’t

  • Don't enter an unsupported trench, even for a quick job.
  • Don't stack spoil or materials right at the edge.
  • Don't park plant or vehicles close to the sides.
  • Don't remove shoring or trench supports while people are inside.
  • Don't jump in or climb out using the supports.

Ask the group

  • Who inspects our excavations, and where are the records?
  • What signs would tell you the sides are about to go?
  • How would we get someone out if a trench collapsed?
  • What services could be under this job?

If it goes wrong

If there's a collapse, call 999 immediately. Don't jump in to dig someone out, as the sides may collapse again. Keep plant and people back from the edge until it's made safe.

Quick check

Five questions to check the talk landed. Ask them out loud, then show the answers.

1. How much can a cubic metre of soil weigh?
  1. About 100 kg
  2. More than 1.5 tonnes
  3. About 500 kg

Answer: More than 1.5 tonnes. HSE says a cubic metre of soil can weigh more than 1.5 tonnes, enough to crush or bury someone.

2. When must a supported excavation be inspected?
  1. Once a week only
  2. At the start of every shift, and after anything that affects it
  3. Only when it's first dug

Answer: At the start of every shift, and after anything that affects it. CDM 2015 regulation 22 requires inspection at the start of each shift and after any event likely to affect stability.

3. Where should spoil be kept?
  1. Right at the edge
  2. Back from the edge
  3. In the trench

Answer: Back from the edge. Spoil near the edge adds load to the sides and can fall in.

4. The side of a trench starts to crack. What do you do?
  1. Finish the job quickly
  2. Get out and report it
  3. Prop it with your shovel

Answer: Get out and report it. Cracks and bulges are warning signs of collapse. Get out first, then report it.

5. What stops vehicles going into a trench when tipping?
  1. A banksman alone
  2. Stop blocks
  3. A cone

Answer: Stop blocks. Stop blocks give a physical barrier so tipping vehicles can't reach the edge.

Running this talk on site?The PDF has a sign-in sheet for your safety file and a poster for the welfare cabin.

Download free PDF

Go further

Trench battered back for safety calculator ›

Sources and qualifications

Source review: 25 November 2026. GB legislation unless another nation is identified. Environmental record periods are for England; check the rules for the site location.

More toolbox talks

See all toolbox talks ›

This talk supports, but does not replace, your site-specific risk assessment, method statement, training and supervision. Free to download, print and share.