Council report · 17 November 2026
Edinburgh’s Meadowbank and Fountainbridge housing schemes are being taken forward through alternative suppliers after their original delivery agreements broke down. The council’s November capital monitoring report records separate difficulties over construction costs and the sharing of risk.
At Meadowbank, the council says significant delays followed a failure to agree costs with the contractor. The agreement has been terminated under its contractual arrangements. At Fountainbridge, the contractor withdrew from the development agreement after standard terms could not be settled, specifically around risk allocation.
The report, prepared for the Finance and Resources Committee on 17 November, says Fountainbridge is progressing through another supplier, but that the change has caused delay. It does not identify the replacement businesses in the relevant passages. Neither passage confirms an imminent start on site.
Meadowbank is a council-led regeneration project combining housing and community facilities with the sports centre that opened in summer 2022. The council’s published masterplan proposes 705 homes, with around 35% affordable and a majority of those for social rent.
The scheme also includes commercial and community premises. Its planning process has advanced in stages, with an application addressing a masterplan condition validated in March 2023. The project page says building heights are intended to reflect the character of the surrounding area.
Fountainbridge occupies the former brewery site bought by the council in 2012. Its published regeneration plans provide for 464 homes, including 186 affordable homes owned by the council. That affordable element comprises 115 social rented homes and 71 for mid-market rent.
The wider Fountainbridge programme includes shops, public space and an extension to Boroughmuir High School. The council says the masterplan was agreed in 2016 following community consultation, with continuing engagement through a sounding board bringing together local stakeholders. Detailed residential design approval followed in 2023.
The latest capital report also puts the individual delays within the wider housing programme. It says acquisitions of completed homes are expected to exceed the budgeted 80, reaching 99 during the year, with £14.4m of spending brought forward. The five-year Housing Investment Programme remains on track and within budget, according to the report.
That wider assessment does not remove the delivery problems on these two sites. For prospective suppliers, the immediate point is that the council is changing the route to delivery. Replacement appointments and revised construction programmes will need to be confirmed separately from the earlier masterplans and procurement arrangements.
Sources · Edinburgh Council capital monitoring report, sections 4.8.2.2–3 · Edinburgh Council Meadowbank project background · Edinburgh Council Fountainbridge project background