Toothing and raking back get mixed up all the time, mostly because both deal with joining or continuing brickwork. They aren’t the same thing, and reaching for the wrong one leaves you with a weak joint or a wall you can’t carry on cleanly. Toothing brickwork ties a new wall into an existing one. Raking back lets you pause a wall and pick it up later in the same line. With either method, success or failure comes down to the joint, which means the mortar and the bond.
What Is Toothing Brickwork?
Toothing brickwork means leaving alternate courses projecting at the end of a wall, or cutting pockets into an existing one, so a new wall can bond into the gaps. Each new course locks into a tooth, which carries the bond across the join instead of leaving a straight vertical joint. Cutting those pockets into brickwork that’s already up is called toothing out.
The method earns its place where a new wall meets an old one: an extension, a T-junction, a boundary wall off an existing house, or a repair that reconnects a split section. The aim every time is continuity, so the two sections are properly bonded rather than two walls simply butting up against each other.
How Toothing Differs From Raking Back
Raking back solves a different problem. When a wall goes up in stages, or stops short for the day, each course is stepped back from the one below to give a staircase profile. That stepped end stays fully bonded, so the next section carries on in the same line without a straight joint and without losing plumb or gauge. Because every bed and perp in a racked end can be filled properly, raking back is generally preferred over leaving toothing for a temporary stopping end. The split is simple:
- Raking Back: Stepped courses on a wall you’ll carry on in the same line, keeping the bond, the plumb and the gauge.
- Toothing: Projecting or cut teeth that bond a separate new wall into an existing one, commonly at a junction.
- Block Bonding: Pockets cut several courses deep, at intervals up the wall, for tying thicker walls together where single teeth won’t do.
- The Shared Goal: All three avoid a continuous straight vertical joint, which is a plane of weakness in any wall.
Choose raking back when the same wall continues. Choose toothing, or a mechanical tie, when a new wall has to join an existing one.
Why Joint Quality Makes or Breaks It
Toothing brickwork lives or dies on the mortar behind the teeth. A tooth with a hollow bed or an unfilled perp is a void, and voids let water track in and give the bond nothing to hold. Get the joints solid and the junction is properly bonded and weathertight. Get them sloppy and cracking along the line of the junction is a common result, sometimes within the first few seasons.
- Full Mortar Joints: Pack every bed and perp joint behind the teeth solid, with no gaps left in the pockets.
- Clean and Dampen the Teeth: Brush off dust and loose mortar, then lightly dampen absorbent brick faces so the fresh mortar grips instead of drying out too quickly. Don’t saturate them.
- Match Gauge and Bricks: Line up the course heights and brick sizes with the existing wall so the bond reads straight through.
- Allow for Movement: A bonded junction doesn’t stop old and new work moving differently. New brickwork expands and old and new foundations can settle at different rates, so where significant differential movement is expected, a tied joint with a movement joint may suit better than toothing. On long runs, provide vertical movement joints at the designed centres, typically around 10 to 12m in clay brickwork and closer in concrete or calcium silicate masonry.
Masonry design, including junctions, ties and movement, is covered by Eurocode 6 (BS EN 1996), with the practical UK recommendations in PD 6697. That’s the design source to work back to when a detail needs justifying.
When to Tooth and When to Use a Wall Starter
Toothing out is slow, it cuts into a wall that’s already standing, and it fails if the new mortar joints are anything less than full. Wall starter kits have taken over much of this work. A stainless steel profile is fixed to the existing wall and ties from it are built into the bed joints of the new one, which avoids the cutting and means the new work isn’t locked to the old wall’s gauge.
- Use Toothing When: A fully bonded, matching connection is the point, the existing wall can safely take the cutting, and a continuous bond needs to show in the face.
- Use a Wall Starter When: Speed and less disruption matter, the gauges don’t match, or a tied joint suits the movement better than a cut bond. Fix the profile and ties to the manufacturer’s instructions; ties are commonly set at around 225mm vertical centres and positioned centrally in the leaf.
- On Cavity Walls: A starter is often used on the inner leaf even where the outer leaf is toothed in, which keeps the inner work simple.
Both routes are sound when done properly. Proprietary wall starter systems are widely used on new homes and extensions, and building control and warranty inspectors generally accept them when the product is suitable for the wall and installed to the manufacturer’s instructions.
Working Safely When Cutting Into Brickwork
Toothing out means cutting masonry that’s already in place, and that brings two real risks. Neither is worth cutting corners on.
Structural Stability
Cutting pockets into a load-bearing wall takes material out of something already carrying weight. Check what the wall supports before you start, provide temporary support such as props or needles where the load calls for it, and remove only what the bond needs. If there’s any doubt over stability, get a structural engineer involved.
Silica Dust
Cutting brick and block with a disc cutter or grinder releases respirable crystalline silica. Breathing it in can cause silicosis, COPD and lung cancer, and the damage is permanent. It’s controlled under the Control of Substances Hazardous to Health Regulations 2002, known as COSHH, with a workplace exposure limit of 0.1mg/m³ averaged over eight hours.
Cut less where you can, use on-tool water suppression or on-tool extraction to an M-class (or H-class) vacuum, and wear suitable RPE such as a face-fit-tested FFP3 mask. Clean up slurry and dust by vacuuming or wet methods, and never dry sweep or blow it around with compressed air. HSE’s guidance on wet cutting sets out the controls in more detail.
Safe work starts with understanding the risks before you begin. Keep developing your construction skills with Tradefox’s guided simulations, where you can practise relevant tasks in a risk-free environment at your own pace.
Conclusion
Toothing and raking back both exist to keep brickwork bonded: toothing for tying a new wall into an existing one, raking back for carrying the same wall on. What holds it all together is the joint, not the method. Full mortar, clean teeth, matched gauge and a connection that suits the expected movement will outlast any shortcut, and safe cutting keeps you and the structure sound while you build it.
Calculators for this job
Free Tradefox calculators that go with this guide:
- Facing brick quantity – How many bricks the new wall needs, with waste.
- Mortar volume estimate – Mortar for full beds and perps, including the toothing.
- Bagged mortar from declared yield – Turn that volume into bags of ready-mix.