Quantities
Facing brick quantity
- where
- bricks per square metre
- brick length (mm)
- perpend joint (mm)
- brick height (mm)
- bed joint (mm)
- net area (m²)
- waste allowance (%)
Explain this equation
This estimates how many facing bricks to order for an area of a single stretcher-bond leaf, including waste.
l and h are the actual brick length and height in mm. j_p is the perpend (vertical) joint and j_b the bed (horizontal) joint. Each brick with its joints takes up (l + j_p) × (h + j_b) of face, and N_m² is how many fit in a square metre. A is the net wall area and w the waste percentage.
A square metre is 1 000 000 mm², so dividing that by the face each brick occupies gives bricks per m². Multiplying by A gives the net count, and (1 + w/100) adds the waste. The ⌈ ⌉ brackets mean round up, because you cannot order part of a brick.
A 215 × 65 mm brick with 10 mm joints occupies 225 × 75 mm, giving about 59.3 per m², usually called 60. Ten square metres with 5% waste comes to 623 bricks.
Watch out: this is an area estimate. Specials, piers, returns, cuts and bond patterns that are not stretcher bond need a separate take-off.
Estimate one stretcher-facing leaf using actual unit sizes and nominal joints.
Enter your values to see the result.
Good to know
Area estimate, not a cutting or bond schedule. Frogs, specials, piers, returns and boundary joints require a separate take-off. Standard example gives 59.259 units/m², often rounded to about 60.
Sources
- Brick Development Association, Designing to Brickwork Dimensions, Technical Guide (2023): 215 × 102.5 × 65 mm brick with 10 mm joints, 225 × 75 mm co-ordinating size
- OpenStax Prealgebra 2e, 9.4 Use properties of rectangles, triangles and trapezoids (area and perimeter formulas)
- OpenStax Prealgebra, 6.2 Solve general applications of percent (percentage additions such as waste and mark-up)
Estimates are not design approval or British Standards compliance checks. Structural arch, retaining-wall, wind, foundation, lintel and masonry-capacity design are not performed. Use the project engineer’s specification.
Worked example
Matching an older house in imperial-height 215 × 73 mm bricks over 24.5 m² net of a new gable and side wall, with 10 mm joints and 8% waste. Each brick takes 225 × 83 mm of face, so N = 1 000 000 ÷ (225 × 83) ≈ 53.5 per m², 24.5 × 53.5 ≈ 1312 net, and ⌈1312 × 1.08⌉ = 1417 bricks. The deeper brick means noticeably fewer per square metre than the usual 60, so do not order from a 65 mm rule of thumb.
Common questions
Why do I need more waste for some bricks than others?
Handmade and reclaimed bricks often have more chipped or out-of-shape units, and jobs with lots of cuts, piers or short returns lose more to offcuts. Plain walls in machine-made bricks need the least allowance.
Should I mix bricks from several packs as I lay them?
Yes, drawing from three or more packs at once helps blend natural colour variation so the wall does not show bands. That is another reason to order the full quantity in one batch.
Does this cover headers in a Flemish or English bond wall?