Temporary works toolbox talk

A free, ready-to-run briefing with an attendance register, quiz, presenter notes, posters and linked sources.

  • 10 minutes
  • For: Anyone working on or near props, shoring, falsework, hoardings or working platforms
  • Last reviewed 25 November 2026
Download free PDFPDF, 1079 KB · 8 pages

Why this matters

Temporary works hold up the permanent works while they're being built. If they're altered, overloaded or used for something they weren't designed for, they can collapse without warning.

Key points

  1. Temporary works include excavation shoring, props, falsework, scaffolds, site fencing, hoardings and temporary stockpiles.
  2. They must be designed, installed and maintained to take any foreseeable loads.
  3. They can only be used for the purpose they were designed and installed for.
  4. A structure must not be loaded so much that it becomes unsafe.
  5. Find out who manages temporary works on your site. They should have the authority to stop work that isn't right.
  6. Only the simplest temporary works go up without a design. Complex ones also get an independent check.
  7. Temporary works must be inspected regularly by a competent person.
  8. Follow the design and manufacturer's instructions exactly. Don't improvise with spare parts.

Do and don’t

Do

  • Find out who the temporary works coordinator is on this site.
  • Build temporary works exactly as the design or drawing shows.
  • Report any prop, support or hoarding that looks damaged, moved or overloaded.
  • Ask before stacking materials on a temporary platform or structure.
  • Stop and ask if what's on site doesn't match the drawing.

Don’t

  • Don't remove, move or borrow props or supports unless the coordinator says it's safe.
  • Don't stack materials on a temporary structure that wasn't designed for them.
  • Don't swap in different parts from what the design specifies.
  • Don't strike falsework or props early to keep the job moving.
  • Don't use temporary works for anything they weren't designed for.

Ask the group

  • Who is our temporary works coordinator, and how do we contact them?
  • Which temporary works are on this site right now?
  • What would you do if a prop was in your way?
  • Have you seen anything stacked on a temporary structure that shouldn't be?

If it goes wrong

If temporary works move, crack or start to fail, get everyone away from the area straight away and keep them out. Call 999 if anyone is trapped or hurt. Tell the temporary works coordinator and your supervisor, and don't try to fix it yourself.

Quick check

1. Which of these is a temporary work?
  1. Excavation shoring
  2. The finished roof
  3. A permanent wall

Answer: Excavation shoring. HSE lists shoring, propping, falsework, scaffolds, site fencing and hoardings as examples of temporary works.

2. A prop is in your way. What do you do?
  1. Move it for a minute
  2. Ask the temporary works coordinator
  3. Swap it for a shorter one

Answer: Ask the temporary works coordinator. Props are part of a design. Removing or moving one can cause a collapse, so check with the coordinator first.

3. Can temporary works be used for a different purpose?
  1. Yes, if it looks strong
  2. No, only for what they were designed for
  3. Only at weekends

Answer: No, only for what they were designed for. CDM 2015 says supports and temporary structures may only be used for the purpose they were designed and installed for.

4. Who can stop temporary works that aren't right?
  1. The temporary works coordinator
  2. Nobody once it's built
  3. Only the client

Answer: The temporary works coordinator. HSE says the coordinator should be formally appointed with authority to stop unsatisfactory work.

5. How often should temporary works be inspected?
  1. Never, once installed
  2. Regularly, by a competent person
  3. Only after an accident

Answer: Regularly, by a competent person. HSE says temporary works such as scaffolding and excavations must be inspected regularly by a competent person.

Running this talk on site?Download the talk, attendance register, quick check and posters.

Download free PDF

Sources and qualifications

Source review: 25 November 2026. GB legislation unless another nation is identified. Environmental record periods are for England; check the rules for the site location.

  • HSE: Temporary works
    Examples, foreseeable loading, design/checks, inspection and management including an empowered TWC; all key points, Do/Don't and quiz.
  • CDM 2015, regulation 19
    Stability, supports, temporary structures and permitted purpose. A TWC is an accepted management approach, not a universally named statutory appointment.

This talk supports, but does not replace, your site-specific risk assessment, method statement, training and supervision. Free to download, print and share.