Free toolbox talk 14 · Site safety
Fire and hot works toolbox talk
Stop fires before they start. A free, ready-to-run briefing for UK sites.
Why this matters
Hot works cause many construction site fires, especially on refurbishment jobs. Sparks can smoulder unseen for a long time and then flare up after everyone has gone home.
Key points
- Hot works include welding, cutting, grinding, brazing and any work with a naked flame or torch.
- First ask: can it be done cold instead, for example by bolting, crimping or a cold-cut saw?
- If hot works are needed, get a hot works permit before you start.
- Clear or protect anything that can burn around the work area, including behind walls and below floors.
- Have the right fire extinguishers at the work area, and know how to use them.
- Keep a fire watch during the work and afterwards, for as long as the permit says.
- Store gas cylinders upright and secured, away from heat, and turn them off at the cylinder after use.
- Keep escape routes clear and know where the fire alarm and assembly point are.
Do and don’t
✓Do
- Check the permit conditions and follow them exactly.
- Use fire blankets and screens to contain sparks.
- Check the area, including hidden spaces, before you leave.
- Keep rubbish and flammable materials to a minimum.
- Raise the alarm early if you see smoke or fire.
✗Don’t
- Don't start hot works without a permit where one is required.
- Don't leave the area as soon as you finish. Keep the fire watch.
- Don't block fire exits, extinguishers or alarm points.
- Don't take gas cylinders into site huts or store them indoors.
- Don't tackle a fire unless you're trained and it's safe to do so.
Ask the group
- Where are the nearest extinguishers and the fire alarm point?
- Could any of our hot works be done cold instead?
- How long is the fire watch on our permits?
- Where is our assembly point?
If it goes wrong
If there's a fire, raise the alarm and call 999. Only use an extinguisher if you're trained, it's safe, and you have a clear way out. Go to the assembly point and don't go back in.
Quick check
Five questions to check the talk landed. Ask them out loud, then show the answers.
1. What should you ask first before hot works?
- Where's the extinguisher?
- Can it be done cold instead?
- Who's on fire watch?
Answer: Can it be done cold instead? The safest hot work is the one you avoid. Cold methods remove the fire risk altogether.
2. When can you leave after finishing hot works?
- Straight away
- After the fire watch set by the permit
- At the end of the day
Answer: After the fire watch set by the permit. Sparks can smoulder unseen. The fire watch continues after the work for the time the permit sets.
3. How should gas cylinders be stored?
- Lying down in the site hut
- Upright, secured and away from heat
- Anywhere out of the way
Answer: Upright, secured and away from heat. Cylinders should be stored upright and secured, outdoors and away from heat sources.
4. What should you do with combustibles near the work?
- Nothing
- Remove them or protect them
- Spray them with water
Answer: Remove them or protect them. Clear or protect anything that can burn, including hidden spaces behind walls and under floors.
5. You see smoke. What's the first thing to do?
- Finish your task
- Raise the alarm
- Go and look for the fire
Answer: Raise the alarm. Raise the alarm early so everyone can get out and the fire service is called.
Running this talk on site?The PDF has a sign-in sheet for your safety file and a poster for the welfare cabin.
Download free PDFGo further
Fire safety in construction: hot works, escape routes and site controls ›
Sources and qualifications
Source review: 25 November 2026. GB legislation unless another nation is identified. Environmental record periods are for England; check the rules for the site location.
- HSE HSG168: Fire safety in construction
Fire prevention, hot work, combustibles, cylinders, fire watch, escape and alarm arrangements; talk sheet and quiz. - HSE: Process fire risks
Avoiding hot work, permit controls, shielding and post-work checks; Do/Don't and poster. A permit requirement may also be a site/insurer rule.
More toolbox talks
This talk supports, but does not replace, your site-specific risk assessment, method statement, training and supervision. Free to download, print and share.