Electricity can kill or cause serious burns, and site conditions are hard on tools and leads. Most electrical accidents on site can be prevented with the right supply, simple checks and leaving electrical work to people trained to do it.
Key points
- Use cordless tools, or single-phase 110 V tools on a centre-tapped-to-earth supply: 55 V from each live conductor to earth.
- In damp or wet conditions, use battery or air-powered tools where you can.
- Use suitable RCD protection of 30 mA or less for 230 V portable tools.
- Press the RCD test button before use. If it doesn't trip, don't use it, and label it faulty.
- Before using a tool, unplug it and check the plug, lead and casing for damage or burn marks.
- Never use leads repaired with tape. Damaged cables must be replaced by a competent person.
- Keep leads out of walkways, water and traffic, and protect them from sharp edges.
- Only trained, competent people can do electrical work, and they must follow correct isolation.
Do and don’t
Do
- Do the pre-use check and follow the inspection schedule. A test label alone does not prove a tool is safe.
- Take damaged tools or leads out of use and report them.
- Unwind extension reels fully so they don't overheat.
- Check for hidden cables before drilling or cutting into walls or floors.
- Switch off and unplug before changing blades, bits or discs.
Don’t
- Don't use a tool with a cracked casing, bare wires or a damaged plug.
- Don't bypass, wedge or ignore an RCD that keeps tripping. It's telling you there's a fault.
- Don't use 230 V equipment on site where 110 V or battery tools can do the job.
- Don't run leads through doorways, puddles or under plant tracks.
- Don't open up or repair electrical equipment unless you're competent and authorised.
Ask the group
- Which of our tools are battery, 110 V or 230 V?
- When did you last check your leads and plugs before use?
- What do we do with a tool that fails its check?
- Where could there be hidden cables on this job?
If it goes wrong
Do not touch a casualty until the equipment and all relevant supplies are made safe. Call 999 and get a first aider. Do not approach damaged cables or metalwork. Take faulty equipment out of use and tell your supervisor.
Quick check
1. On single-phase 110 V centre-tapped-to-earth, what is each live to earth?
- 110 V
- 55 V
- 230 V
Answer: 55 V. Single-phase 110 V centre-tapped-to-earth is 55 V to earth; a three-phase 110 V system is different (about 64 V).
2. What should an RCD's tripping current be for personal protection?
- Not more than 30 mA
- 300 mA
- 3 A
Answer: Not more than 30 mA. Use a suitable RCD rated 30 mA or less for additional protection. It cannot protect against every electric shock or replace safe equipment.
3. The RCD keeps tripping. What do you do?
- Wedge the switch on
- Stop and get the fault checked
- Plug into a different socket and carry on
Answer: Stop and get the fault checked. An RCD trips because of a fault. Never bypass it. Get the system checked.
4. You find a lead repaired with insulating tape. What now?
- Use it carefully
- Take it out of use and report it
- Add more tape
Answer: Take it out of use and report it. Taped repairs aren't safe. Damaged cable should be replaced by a competent person.
5. What is the pre-use checking rule in this toolbox talk?
- Before every use
- Once a year
- Never
Answer: Before every use. Check before every use. Formal inspection and test intervals follow a risk-based maintenance plan; there is no universal annual PAT requirement.
Running this talk on site?Download the talk, attendance register, quick check and posters.
Download free PDFSources and qualifications
Source review: 25 November 2026. GB legislation unless another nation is identified. Environmental record periods are for England; check the rules for the site location.
A4-related review: temporary construction installations need competent design using the applicable requirements, including Section 704 where in scope. Select RCD type/protection for the actual loads; an RCD cannot substitute for sound equipment or correct isolation.
A4 basis: published IET guidance; the full licensed standard was not available for clause-by-clause checking. This is a source review, not installation certification. IET current edition.
- HSE HSG141: Electrical safety on construction sites
Site supply design, battery/reduced-voltage hierarchy, single-phase 55 V versus three-phase 64 V to earth, correct isolation and maintenance; key points and quiz. - HSE: Electrically powered equipment
Suitability, 30 mA additional protection limitations, checks, leads, damp/conductive environments and RCD testing; Do/Don't and quiz. - HSE: Portable appliance testing FAQs
Risk-based inspection/testing, no universal annual PAT rule, labels not proof of safety; quiz 5 and presenter notes. - IET: Isolation and switching devices (2026)
A4 context: suitable isolation devices, all sources and isolation versus functional switching. Electrical design remains the competent designer's task.
This talk supports, but does not replace, your site-specific risk assessment, method statement, training and supervision. Free to download, print and share.