Download free PDFPDF, 1075 KB · 8 pages

Why this matters

The Construction (Design and Management) Regulations 2015, known as CDM, set out who is responsible for health and safety on a construction project. They apply to every project, big or small, including work on people's homes. Knowing your part helps keep everyone safe.

Key points

  1. CDM 2015 covers construction in Great Britain, including domestic work.
  2. Clients, designers, contractors and workers have duties. Principal designers and principal contractors are required where more than one contractor is involved.
  3. As a worker, only take on work you're competent for, or are trained and supervised to do safely.
  4. Follow site rules and procedures, and cooperate with whoever controls your work and the principal contractor.
  5. Tell whoever controls the work about any risks you find, to you or to anyone else.
  6. You should get a site-specific induction, plus the information, instruction and supervision you need.
  7. Suitable welfare facilities must be in place from the start and kept up throughout the job.
  8. Your employer must consult you, or your representatives, on health and safety that affects you.

Do and don’t

Do

  • Pay attention at your site induction and ask about anything you don't understand.
  • Follow the site rules and the method for your job.
  • Report risks to whoever controls your work straight away.
  • Speak up if you're asked to do work you're not trained for.
  • Tell your supervisor if welfare facilities are missing, dirty or broken.

Don’t

  • Don't start work on a new site without an induction.
  • Don't take on a task you're not competent or trained to do.
  • Don't ignore a risk because it's another trade's problem.
  • Don't change the agreed way of working without checking first.

Ask the group

  • Who is the principal contractor on this job, and who controls our work?
  • What did our site induction cover, and was anything missed?
  • Who would you tell if you spotted a risk on this site?
  • Are the welfare facilities here good enough?

If it goes wrong

If you see something dangerous, stop and tell whoever controls the work straight away. If someone is hurt, call 999 and get a first aider. If your concern isn't dealt with, raise it with the principal contractor, your safety representative or HSE.

Quick check

1. Which projects does CDM 2015 apply to?
  1. Only big commercial sites
  2. All construction projects, including domestic work
  3. Only projects over 30 days

Answer: All construction projects, including domestic work. CDM applies to all construction projects. On domestic jobs, the client duties usually pass to the contractor or principal contractor.

2. You spot a risk that could hurt another trade. What should you do?
  1. Leave it, it's not your work
  2. Tell whoever controls the work on site
  3. Wait until the end of the day

Answer: Tell whoever controls the work on site. HSE says workers must report risks they find, whether they affect themselves or anyone else.

3. What should every worker get on a new site?
  1. A site-specific induction
  2. A free hard hat only
  3. Nothing, if they're experienced

Answer: A site-specific induction. Under CDM, principal contractors must make sure all workers have a site-specific induction.

4. You're asked to do work you've never been trained for. What do you do?
  1. Have a go
  2. Say so, and only do it with training and supervision
  3. Ask a mate to watch

Answer: Say so, and only do it with training and supervision. Workers should only take on work they're competent for, or are trained and supervised to do safely.

5. When must welfare facilities be in place?
  1. From the start of the construction phase
  2. After the first month
  3. Only on big sites

Answer: From the start of the construction phase. Principal contractors must make sure suitable welfare is provided from the start and maintained throughout.

Running this talk on site?Download the talk, attendance register, quick check and posters.

Download free PDF

Sources and qualifications

Source review: 25 November 2026. GB legislation unless another nation is identified. Environmental record periods are for England; check the rules for the site location.

  • HSE: CDM workers
    Competence, cooperation, risk reporting, instruction and induction; key points 3-6, Do/Don't and quiz.
  • HSE: Principal contractors
    More-than-one-contractor trigger, coordination, welfare and consultation duties; key points 1-2 and 7-8.
  • HSE: Domestic clients
    Application to domestic projects and transfer of domestic client duties.

This talk supports, but does not replace, your site-specific risk assessment, method statement, training and supervision. Free to download, print and share.