Tradefox

Tradefox – Build Skills

Learn Construction

‹ All insulation and retrofit calculators

Part L compliance

Part L limiting U-value check for renovation (existing dwellings)

Δt=Ue−UthΔl=Ul−Up
where
Δt
existing U-value above the threshold (W/m²K)
Ue
existing U-value of the element (W/m²K)
Uth
threshold U-value (W/m²K)
Δl
margin of the proposed U-value below the limit (W/m²K)
Ul
limiting (improved) U-value (W/m²K)
Up
proposed U-value after work (W/m²K)
Explain this equation

Checks a renovation against the Approved Document L rules for existing dwellings: whether the element must be upgraded, and whether the proposed U-value meets the limit.

When you renovate a wall, roof or floor whose U-value is worse than the threshold (a positive Δ_t), Part L expects it to be upgraded to the limiting U-value, as long as that is technically, functionally and economically feasible. A positive Δ_l means your proposed U-value is at or better than the limit.

Two simple differences against the values in the Approved Document tables.

Sense check: a solid wall at 2.0 is 1.3 above the 0.70 threshold, so it should be upgraded; a proposed 0.28 is 0.02 better than the 0.30 limit for internal or external wall insulation.

Watch out: if meeting the limit is not feasible (for example payback over 15 years or excessive loss of floor area), aim for the best reasonable U-value and record why. Building control may need notifying.

Compares an existing and a proposed U-value with the Approved Document L figures for renovating thermal elements in existing dwellings.

W/m²K
W/m²K
W/m²K
W/m²K

Enter your values to see the result.

Good to know

Approved Document L Volume 1 (England), Table 3.3 of the 2026 edition and Table 4.3 of the 2021 edition (same values): threshold / improved U-values in W/m²K are roof 0.35 / 0.16; wall with cavity insulation 0.70 / 0.55; wall with internal or external insulation 0.70 / 0.30; floor 0.70 / 0.25. New or replacement elements in an existing dwelling (extensions, new walls) must meet roof 0.15, wall 0.18 and floor 0.18 (Table 3.2). The 2026 edition comes into force on 24 March 2027 for most work; until then the 2021 edition applies, subject to the transitional arrangements. Renovation of more than 50% of an element's surface, or re-rendering, re-plastering or re-roofing, triggers the requirement. Wales and Scotland have their own documents and values.

Common mistake

Applying the new-build or extension values (0.18 walls) to the upgrade of an existing solid wall, or ignoring the requirement entirely when re-plastering or re-rendering more than half a wall.

Limits

Element-by-element check for England. Does not cover the alternative whole-dwelling approach, conservation-area or listed-building exemptions, or the Part C moisture check that must accompany an upgrade. Always confirm with building control.

Sources

Results are calculations from the published methods and figures shown, and depend on the data you enter. Follow BS EN ISO 6946, BS 5250, PAS 2035, Building Regulations Part L and manufacturers’ data. Whole-house retrofit needs a qualified retrofit assessor and coordinator.