Tradefox

Tradefox – Build Skills

Learn Construction

‹ All bricklaying calculators

Geometry

Rise, run, slope & rake

L=x2+y2θ=atan(yx)G=yx×100n=xy
where
L
slope length (m)
x
horizontal run (m)
y
vertical rise or fall (m)
θ
angle (degrees)
G
gradient (%)
n
gradient as 1 in n
Explain this equation

This turns a horizontal run and a vertical rise into the sloping length, the angle, the percentage gradient and the 1 in n ratio.

x is the horizontal run and y the vertical rise, both in metres; a negative y means a fall. L is the length measured along the slope. θ is the angle from horizontal in degrees. G is the gradient as a percentage, and n is the run per unit of rise, as in 1 in n.

The run, rise and slope form a right-angled triangle, so L comes from Pythagoras and θ from the tangent, rise over run. The gradient is rise over run expressed per hundred, hence × 100. 1 in n is that ratio inverted.

A 4 m run with a 1 m rise gives a 4.12 m slope, about 14°, 25%, or 1 in 4. Doubling the rise roughly doubles the gradient but does not double the angle.

Watch out: with zero rise the slope is level and 1 in n has no meaning, so the calculator shows 0. A falling slope gives negative values.

Calculate a rake or fall from horizontal run and vertical rise.

m
m

Enter your values to see the result.

Estimates are not design approval or British Standards compliance checks. Structural arch, retaining-wall, wind, foundation, lintel and masonry-capacity design are not performed. Use the project engineer’s specification.

Worked example

A garden path ramp rises 0.5 m over a 6 m horizontal run. L = √(6² + 0.5²) ≈ 6.02 m, θ = tan⁻¹(0.5 ÷ 6) ≈ 4.8°, G = 0.5 ÷ 6 × 100 ≈ 8.3%, which is 1 in 12. Order edging and paving on the 6.02 m sloping length, and check the 1 in 12 against any access requirements the client has asked for.

Common questions

Why is the sloping length barely longer than the run?
On gentle slopes the difference is small, here only about 20 mm in 6 m. It only becomes significant on steep slopes, such as roof pitches or banks, where using the plan length would short you on materials.

How do I measure the rise on site?
Set up a level or laser at the top, read a staff at the top and bottom of the slope, and take the difference. A long straight edge and spirit level works over short distances, stepping down the slope.

Are 1 in 12 and 12% the same thing?
No. 1 in 12 is one unit up for twelve along, which is about 8.3%. A 12% gradient is steeper, about 1 in 8.3, so always check which form a specification uses.